Battery Storage Investment Calculator

Base case

Fictional project “Batteriespeicher Musterfeld” · 50 MW / 100 MWh (2 h) · Germany · a tolling contract and the market with reserves

Illustrative calculation — not investment, tax or legal advice. Fictional case. Prices to 30 Sep 2026.

How the model works →Sources →

Investor IRR −0.7%

What would the toll have to pay?

At this toll price, the project does not earn the hurdle rate.

The investor breaks even at a toll of €220,000 per MW a year — against €120,000 in these inputs.

Tolling offers quoted in the market for 2-hour batteries: €110,000–€150,000 per MW a year (a benchmark, not an offer).

aFRR capacity is offered from May 2028 — prequalification takes three months after commercial operation — and only in the years it pays more than trading: 2028, 2029.

Market revenue of the whole battery in 2030: €69k per MW in the model, against €156k in FfE/PwC’s forecast (September 2026) and €125k in Modo Energy’s (March 2026; its April update cut lifetime revenue by 16%).

The three reserve saturation paths
PathInvestor IRRBreak-even toll
Central (FfE/PwC)−0.7%€220,000
Fast exit−0.7%€221,000
Slow−0.5%€218,000

Reserves and intraday trading on cautious assumptions: aFRR capacity only in the years it pays more than trading, intraday as a fixed uplift on the day-ahead margin; no FCR and no income from aFRR activation. Nothing is tuned to reach a target.

Why the break-even price is above the market
  1. A cautious market: intraday trading adds 15% to the day-ahead margin, where FfE/PwC’s forecast for 2030 implies about 100%; and reserve prices fall as batteries flood the market, so aFRR beats trading only in the first years.
  2. A fully amortising 10-year loan instead of the usual 7-year mini-perm with 70–80% debt.
  3. Investment of about €765 per kW for 2 hours, against about €700 in Modo Energy’s benchmark.
  4. A 15-year life, with no value after it.

How the money flows

In 2029, the first full year, the toller pays €96k per MW for 80% of the battery; the rest earns €14k per MW on the market — €7k from day-ahead trading, €1k from intraday and €8k from aFRR capacity, less the optimiser’s fee — €110k per MW in all.

Operating costs and grid charges take €24k per MW, which leaves EBITDA of €86k per MW.

Building the battery costs €38.3m (€765 per kW). The bank looks at the low spread path and lends €17.8m — 44% of the cost without VAT; the owner pays in €24.3m.

Batteries are added in 2038 to restore capacity, and the inverters are overhauled in 2040. The company keeps the cash these need instead of paying it out.

The investor earns −0.7% a year against a hurdle of 12%.

Revenue and cash by year

€ million, nominal.

  • Toll fee
  • Market trading
  • Operating costs
  • Cash for debt service
−20246202820302032203420362038204020422043

Model and text: Igor Sabodakha · Prices: Bundesnetzagentur | SMARD.de via Energy-Charts (CC BY 4.0), derived statistics only; aFRR: German TSOs (regelleistung.net) · Methodology v1.3 R3.1 · revenue library DE v1